One Day Set - One Week to Start Up

One Day to Set, 1 Week to Fire Up, Test, Inspect and Turnover

 

Project Specifics

→  Location – North Carolina

→  Sector – Residential  

→  Conveyance – MRL Traction

→  Total Travel – 56 ft. 

→  Stories – 5 

Every project comes with challenges. This project had the need to be completed and functional before the end of the year. Only Resolute Elevator can deliver the high-quality solution that was needed. We met the challenge completing the project months before the deadline.

Our self-supporting steel hoistway arrives with the cab, entrances, rails, equipment, means of conveyance and wiring already installed at the factory. On site, the team lifts the system into place, bringing months of planning and craftsmanship together in a single day.

For owners, architects, and general contractors, that means fewer trades to coordinate, less on-site disruption, and a faster path toward project completion.

The startup, commissioning, and inspection follow the set. For building owners it means better quality elevator, non-proprietary equipment and speed to revenue.

This project includes 2-hour fire rated structural steel hoistway with hoist beam (carries floor loads just like a CMU hoistway), pit ladder, pit light & switch, GFCI outlet & code required hoistway lighting. Marine grade vinyl wrap for protection during shipping and construction.

We take the elevator installation out of the critical path to project completion for the GC and owner.

 

NEXT STEP

This new successful project is just one example of the high-quality, speed of delivery, ease of inclusion, and innovation you can expect from Resolute Elevator.  We encourage you to ask questions and find out more or begin the next step of including the Resolute Elevator System in your project. Begin by downloading the drawings.